Our experience with ‘Big Box’ projects includes over 20 projects. The WDG team has built warehouses, distribution centers, motorpools, industrial facilities and manufacturing plants. Clients include, but are not limited to, Fed Ex, Caterpillar, State of Indiana, Penn Products, Bindley Western, USF Holland and Universal.

Experience

Fed Ex, South Point, OH

Work performed: New build; Ground distribution center
Contract amount: $4,300,000
Contracted with: Scannell
 Properties Indianapolis, Indiana
Start date: January 2012
Completion date:
 Marach 2013

FedEx, Hot Springs, Arkansas

Work performed: New build; Ground distribution center
Contract amount: $2,700,000
Contracted: August 2012
Completion date: June 2013

American Tire Distribution

Work performed: New build; Distribution Center
Contract amount: $5,800,000
Contracted with: Scannell Properties Indianapolis, Indiana

Start date: October 2012
Completion date: June 2013

Camden Iron and Metal

Work performed: Build a new motor building
Contract amount: $2,000,000
Contracted with: Camden Iron and Metal
Start date: January 2013
Completion date: April 2013

FedEx, Santa Fe, New Mexico



Work performed: New Build; Ground distribution center
Contract amount: $3,000,000
Contracted with: Scannell Properties, Indianapolis, Indiana
Start date: November 2008
Completion date: June 2009

Fed Ex, Henrietta, New York



Work performed: Addition to existing Fed Ex Ground Facility
Contract amount: $2,370,000
Contracted with: Scannell Properties, Indianapolis, Indiana
Start date: June 2009
Completion date: October 2009

Fed Ex Ground Facility, Austin, Texas



Work performed: Pre-engineered metal building with tilt up concrete walls
Contract amount: $6,800,000
Contracted with: Scannell Properties, Indianapolis, Indiana
Start date: January 2008
Completion date: October 2008

Fed Ex, Midland, Texas

Work performed: New build of ground distribution center
Contract amount: $2,700,000
Contracted with: Scannell Properties, Indianapolis, Indiana
Start date: October 2008
Completion date: June 2009

FedEx, Albany, NY



Work performed: New build ground distribution center
Contract amount: $16,500,000
Contracted with: Scannell Properties, Indianapolis, Indiana
Start date: January 2011
Completion date: December 2011